Wednesday, September 23, 2009

Devaun Park Mathews Update September 26, 2009

Happy Saturday! This past week, all of the exterior porch and deck hand rails/pickets, have been completed along with the interior insulation, sheetrock, hardwood flooring and stair rails. Tile work began this past week and will continue into next. Cabinet installation will begin next week and interior trim the following week.

All the best,

The Whitney Blair Team

Tuesday, September 8, 2009

Devaun Park Mathews Update September 8, 2009

Happy Tuesday! We continue to make significant progress on your new home in Devaun Park, as noted by the photos below. Insulation is complete, drywall to follow....


All the best,

Your Whitney Blair Inc. Team



Deck and porch posts are now set

Staircase is in place!





2nd floor bath tub in place

Check out the front porch and porch ceiling detail


View from the 2nd floor porch



Mario hard at work on the back porch hand rail and pickets